Beech Street

The City of Campbell River is expanding improved services and infrastructure along Beech Street from Alder Street to 10th Avenue.

Frequently Asked Questions

New Schedule For Beech Street Renewal - July 2022

Newsletter #2 - July 2022

Newsletter #1 - May 2022

Project Details at a Glance

This stage of the downtown upgrades is the result of an opportunity presented by proposed construction of a mixed residential-commercial building on a currently-undeveloped lot on the street (325 Beech Street).

The Refresh Downtown Strategy was completed in 2017 to prepare advanced plans for upgrades through the downtown core, which could be easily implemented when opportunities arose in the area. The Beech Street Renewal upgrades are an example of such an opportunity this strategy was prepared for, which can be achieved because of the preparatory work done.

Based on the feedback from the community and input from technical advisors, the Refresh Downtown strategy identifies priorities for the area and establishes an aesthetic standard.

Work will include:

  • Infrastructure updates: new water, sewer and storm mains and services
  • New roadways: new roadway constructed to meet Urban Local Commercial Standards
  • Pedestrian-friendly upgrades: lighting, crosswalks, boulevards
  • Aesthetics: new surface finishes matching the adjacent Downtown Revitalization Project (including new lighting, tree planting and landscaping

Conceptual drawing of anticipated upgrades to Beech St, between Alder and 10th Ave

Conceptual drawing of anticipated upgrades to Beech St, between Alder and 10th Ave

Parking Changes

The Beech Street Renewal Project and development of 325 Beech Street will displace 70 less public parking spots.

The City monitors parking capacity regularly and has continued to review usage rates in the area. Currently on average parking is used at 63% capacity in the downtown area – of 1,441 spots in the downtown area there are approximately 500 spots regularly available within a short walk. 

Proposed site for multiuse development at 325 Beech Street.)
Proposed site for multiuse development at 325 Beech Street.

 

Timeline and Funding

Upgrades are expected to be completed by fall 2023.

The project is currently estimated to cost $4.2 million, funding for which will be allocated within existing budget and will not result in increased taxes for the community. This cost will be further refined/confirmed as the work approaches, reflecting rapidly changing costs of construction worldwide.

Questions? Call 250-286-5700 or Email us capitalprojects@campbellriver.ca

 

Links

NEWS RELEASES

Featured
What's New
Jun 30, 2022 Canada Day 2022 Events
Jun 22, 2022 HOW’S THE WATER?
Jun 22, 2021 Summer Fire Safety
Feb 03, 2021 Calling young artists!
Jan 02, 2020 2019 Year-in-Review
Nov 01, 2018 New marine habitat
Nov 02, 2017 CRadvantage goes live!
Jul 25, 2017 Chalkfest returns!
Jun 30, 2017 Celebrate Canada Day!
Jan 09, 2017 2016 Year-in-Review
Dec 20, 2016 Tourism update!
Nov 16, 2016 Fire Chief for a Day
Oct 11, 2016 Afternoon garage fire
Sep 20, 2013 Walk-ability Survey
Sep 20, 2013 Tidemark grant in aid
Sep 21, 2013 ECAP
Sep 21, 2013 George Paul Passing
Sep 21, 2013 MyCity info update
Sep 21, 2013 Seed saving
Oct 08, 2013 Fire Prevention Week
Feb 24, 2014 Roads Update
Sep 24, 2014 Fall Fire Safety
Dec 18, 2014 Fawn Rd. house fire
Feb 06, 2015 Fire crews kept busy
Feb 26, 2015 Mobile home fire
Jun 26, 2015 New art summer camps
Dec 04, 2015 Storm Warning!
Jan 04, 2016 Jan. 1 City Currents
Jan 07, 2016 New Robron Field open!
Upcoming Events
Apr 28, 2023 Youth Carnival Night
May 13, 2023 A Walk To Remember
May 28 - Jun 04, 2023 Spring Go By Bike